TAIPEI (Taiwan News) — Taipower Chair Tseng Wen-sheng (曾文生) said Monday that the country's power industry must speed up investment decisions to keep pace with the technology sector, shortening planning horizons from about 10 years to five or even three years.
Speaking at a press conference ahead of the Net-Zero Taiwan and Energy Taiwan exhibition, Tseng said electricity security would depend not only on having sufficient generation capacity but also on whether the grid could deliver power to where it is needed while coordinating with renewable energy sources and energy storage facilities, per CNA.
As AI drives demand for computing power, electricity is becoming an increasingly important part of the semiconductor and technology supply chains, Tseng said. Thus, Taipower can no longer act solely as an electricity supplier, he said.
Parts of its operations must become more closely aligned with the technology industry, including understanding companies' investment schedules, financial arrangements, and supply chain needs. Businesses seeking more renewable energy also need to coordinate with suppliers on green electricity purchases, renewable energy certificates, and storage systems, Tseng said.
Tseng said Taiwan's existing power resources and investment plans were sufficient to support current domestic industrial development, citing Taiwan's investment in natural gas-fired power generation, which ranked third globally in 2024 and sixth in 2025. However, he warned that electricity demand from AI applications could grow rapidly and prove difficult to predict.
He said computing demand will not only be concentrated among large cloud service providers, as some companies may build their own data centers to conduct computing locally to protect confidential information. This could spread electricity demand across multiple locations, complicating grid planning, per UDN.
Taipower is closely monitoring growth in distribution networks and general high-voltage electricity consumption, Tseng said. If demand for computing power rises rapidly, the challenge will be ensuring that the grid can deliver electricity to customers in time, rather than simply increasing generation capacity.
Tseng said Taipower hopes to establish more communication platforms with technology companies, renewable energy developers, and other industries through exhibitions and forums to discuss future market arrangements and commercial cooperation.
Asked about speculation that Taipower might ask major electricity users such as TSMC to finance power plant projects, Taipower Spokesperson Huang Mei-lien (黃美蓮) said the company would continue discussing potential electricity investment plans with high-tech businesses, per TechNews.
Such discussions do not mean Taipower is transferring responsibility for future electricity supply to manufacturers, she said.