TAIPEI (Taiwan News) – Taichung said Monday that construction of Taiwan Semiconductor Manufacturing Co.’s expanding 1.4‑nanometer fab at the Central Taiwan Science Park is progressing steadily and ahead of schedule, according to a press release.
Mayor Lu Shiow-yen (盧秀燕) inspected the site accompanied by TSMC Vice President Arthur Chuang (莊子壽). They discussed the latest developments and future investment needs.
Taichung's Economic Development Bureau said Plant 1's main structure is underway; Plant 2 broke ground in October 2025, with the foundation now complete; Plant 3 has obtained its permit, while Plant 4's application is being approved. The finished site is expected to create about 4,500 jobs.
Contractors said that Plant 1 should be completed before April 2027 and ready for test production in the fall. They added that with successful trial runs, full production can begin in 2028, per the Commercial Times.
TSMC ran various simulations to minimize safety hazards. It also introduced AI image recognition systems that detect and warn workers of oversights and potential heat strokes on hot days.
Lu also highlighted TSMC's contributions to Taichung's reforestation, specifically along Provincial Highway 74, overpasses, and the nearby Daan coastline. The city added that the TSMC site plans to use 100% recycled water and renewable energy in the future.